If you are building, remodeling, adding a room, replacing regulated electrical, plumbing or HVAC work, opening a commercial space, installing a pool, or changing a property in unincorporated DeKalb County, the main office is the DeKalb County Planning & Sustainability Department — Permits, Plan Review & Inspections Division.
The process is easier when you start in the right place. DeKalb County contains several incorporated cities, and those cities may issue their own permits. A Decatur, Atlanta, Stone Mountain, Tucker or other mailing address does not by itself tell you which permitting office controls the property.
DeKalb County says that projects inside an incorporated DeKalb municipality are generally handled by that city’s permitting office. Use the county’s official jurisdiction map first.
Check DeKalb permitting jurisdictionIf the property is actually within Atlanta city limits, use our Atlanta Building Department guide instead of assuming DeKalb County is the permitting authority.
DeKalb County Building Department Contact Information
| Service | Current information |
|---|---|
| Department | DeKalb County Planning & Sustainability — Permits, Plan Review & Inspections |
| Office address | 178 Sams Street, Decatur, GA 30030 |
| Permit information | 404-371-2155, option 3 |
| Permit email | permitinfo@dekalbcountyga.gov |
| One-Stop counter hours | 8:30 a.m.–4:00 p.m. |
| Online permitting | DeKalb e-Permitting Portal |
| Forms and checklists | Official Resources & Tools |
Some older county PDFs still display previous office information. For a 2026 visit, use the current department page and the current address at 178 Sams Street.
Do You Need a DeKalb County Building Permit?
DeKalb County Code generally requires a permit before construction, alteration or repair of a building or structure and before regulated mechanical, gas, plumbing, electrical or energy-system work. The county code contains a narrow exception for ordinary repairs to a single-family residential building when the wholesale cost does not exceed $3,000.
| Project | What to expect |
|---|---|
| New single-family home or duplex | Building permit, site/development review, plan review and required inspections. |
| Home addition | Permit and zoning/site review generally apply. Additional engineering may be needed for some projects. |
| Structural renovation | Building permit and plan review may be required based on the work. |
| Electrical work | Electrical permit; county states licensed electrical contractors submit these permits. |
| Plumbing work | Plumbing permit; licensed plumbing contractor requirements apply. |
| HVAC / mechanical work | Mechanical permit; licensed mechanical contractor requirements apply. |
| New commercial construction | County states new commercial construction begins with a Land Development Permit (LDP), followed by applicable building review. |
| Demolition | LDP requirements and the county demolition checklist apply. |
| Swimming pool | Building application, Board of Health approval, fencing and electrical approval are part of the county’s published requirements. |
| Retaining wall | County lists walls 4 feet or higher, when not part of the primary building foundation, as requiring a specialty permit. |
| Commercial tent | A permit is required when a tent is used on commercial property or for a commercial purpose. |
How to Apply for a DeKalb County Building Permit
1. Confirm the property is under DeKalb County jurisdiction
Open the county’s jurisdiction checker, locate the property, and confirm that the county—not an incorporated city—is the permitting authority.
Open jurisdiction checker2. Check zoning, setbacks and site restrictions before drawing final plans
Confirm the parcel’s zoning, required setbacks, lot coverage or impervious-surface limits, overlay rules, floodplain conditions, stream buffers, tree requirements and historic-district status when relevant. Fixing a zoning conflict before permit submittal is much easier than redesigning after review comments.
DeKalb zoning information DeKalb GIS & property tools3. Match your work to the correct permit type
Decide whether you need a residential building permit, commercial permit, electrical permit, plumbing permit, HVAC permit, pool permit, sign permit, demolition approval, retaining-wall permit or another specialty service. More than one permit can apply to the same job.
Official permit types4. Gather the documents before opening the application
Have the property address, owner information, applicant information, contractor details, project description and required drawings ready. Depending on the project, you may also need a site plan, building elevations, engineering documents, sewer/watershed approval, environmental forms, an owner affidavit or an authorized permit-agent form.
Open forms, guides & checklists Building permit application5. Submit the permit application online
Open DeKalb’s e-Permitting portal and sign in or create an account if required. Select the permit category, enter the job address carefully, provide the project and contractor information, attach the required documents and submit the record.
Save the application or permit number immediately. You will use it to follow review comments, payments, inspections and final approval.
Open e-Permitting6. Upload plans and respond to review comments
Projects requiring plan review are routed through the county’s ProjectDox process. County reviewers may check building, zoning, land development, environmental, fire, watershed or other disciplines depending on the scope. If corrections are issued, update the plans and resubmit the requested material rather than creating an unrelated new application.
The county’s current permit page contains the live Submit Plans and Check Status in ProjectDox links, which is safer than bookmarking an old ProjectDox address.
Open official plan-review page7. Pay assessed fees and wait for permit issuance
Review the county invoice before payment because the final amount can include the permit fee, technology fee, trade fees, plan revisions, land-development charges or other project-specific costs. Do not treat application submission as permission to begin regulated construction.
8. Post the permit and complete inspections in the correct order
Keep the permit card visible at the site and maintain the county-approved construction and site plans there. Request required inspections before work is concealed. After all required final approvals are complete, finish the Certificate of Occupancy process when a CO is required.
Schedule an inspectionDocuments Commonly Needed
Requirements vary by project, but preparing these items before submission can save a surprising amount of back-and-forth.
- Completed building permit application.
- Correct property address and owner information.
- Project description and proposed use.
- Site plan or survey when required.
- Building plans and elevations for applicable construction.
- Contractor name, state license information and business-license information when applicable.
- Authorized Permit Agent Form if someone applies on behalf of the licensed contractor.
- Homeowner’s Affidavit when an eligible owner is taking responsibility for work on the owner’s primary residence.
- Environmental, erosion-control and tree-related documents when applicable.
- Watershed or sewer-capacity approval for projects that trigger those reviews.
- Historic-preservation approval if the property is in a regulated historic district.
- Engineering letters or calculations for structural work when requested.
DeKalb’s residential guide specifically calls for contractor registration, zoning review, proof of ownership when tax records have not yet updated, floodplain review when applicable, stream-buffer review, a site plan, building elevations, environmental information and sewer-related documentation.
View the official single-family permit guideDeKalb County Building Permit Fees in 2026
The county’s current 2026 Development Services fee schedule was last updated June 8, 2026. The amount you actually owe can vary with project valuation, permit type, trade work and additional reviews.
| Fee item | Published 2026 amount |
|---|---|
| Building permit minimum | $175 |
| Technology fee | $20 per permit, additional |
| Electrical permit minimum | $100 + $20 technology fee |
| Plumbing permit minimum | $100 + $20 technology fee |
| HVAC permit minimum | $100 + $20 technology fee |
| Interior tenant finish — move in as is | $175 |
| Certificate of Occupancy | $50 |
| Temporary CO — non-residential only | $25 |
| Residential site-plan revision | $25 |
| Other plan revision | $50 |
| Resubmittal after the second resubmittal | 25% of permit fee |
| First reinspection | $25 |
| Second reinspection | $50 |
| Third and later reinspection | $100 |
| After-hours inspection | $50/hour, 4-hour minimum |
| Working without a valid permit | Double permit fee listed in the current schedule |
For new construction, DeKalb’s schedule uses ICC Building Valuation Data to determine construction valuation and applies a factor of 0.0065. In practical terms, that is $6.50 per $1,000 of calculated construction valuation, subject to the county’s minimum and other applicable charges.
View official 2026 fee schedule2026 Building Codes Used in DeKalb County
Georgia’s updated State Minimum Standard Codes took effect January 1, 2026. DeKalb County also published a transition notice explaining how the change affects older applications and projects.
| Code area | 2026 state standard |
|---|---|
| Building | 2024 International Building Code with Georgia Amendments |
| Residential | 2024 International Residential Code with Georgia Amendments |
| Plumbing | 2024 International Plumbing Code with Georgia Amendments |
| Mechanical | 2024 International Mechanical Code with Georgia Amendments |
| Fuel gas | 2024 International Fuel Gas Code with Georgia Amendments |
| Electrical | 2023 National Electrical Code with 2026 Georgia Amendments |
| Fire | 2024 International Fire Code, with applicable state fire requirements |
| Swimming pools and spas | 2024 International Swimming Pool and Spa Code with Georgia Amendments |
| Energy | 2015 International Energy Conservation Code with Georgia supplements and amendments |
DeKalb’s 2026 transition rules
- Georgia’s 2024 code family became effective January 1, 2026.
- LDP applications submitted before January 1, 2026 continue under the code editions applicable to those projects.
- Building-permit applications without an LDP submitted on or before February 28, 2026 could use the prior 2018 editions under the county’s published grace period.
- Applications without an LDP submitted on or after March 1, 2026 must comply with the 2024 code editions.
- Projects already in review or under construction remain under the code edition tied to the issued permit.
For the current statewide code list and downloadable Georgia amendments, use the Georgia Department of Community Affairs. If you are comparing requirements with nearby Atlanta, our Atlanta building code guide explains the same Georgia code family in a city-permitting context.
How DeKalb County Building Inspections Work
The most important inspection rule is simple: do not cover work that must be inspected. DeKalb’s residential and commercial inspection guides state that required inspections must be requested before concealment. County-approved plans and the permit card should remain at the jobsite.
Typical residential inspection order
- Temporary power pole, when applicable.
- Initial environmental inspection after erosion controls, construction drives and tree-save fencing are installed.
- Footing/foundation inspection before concrete placement.
- In-slab electrical, plumbing or HVAC inspections, when applicable.
- Structural slab inspection.
- Damp-proofing inspection before backfill where applicable.
- Pre-cladding inspection after the weather-resistive components are installed but before exterior cladding.
- Electrical, plumbing and HVAC rough inspections.
- Building framing/insulation inspection after required rough inspections pass.
- Environmental pre-grading inspection before permanent vegetation where required.
- Electrical, plumbing and HVAC finals.
- Fire Marshal final when applicable.
- Environmental final with required as-built, water-quality or tree documents where applicable.
- Final building inspection.
- Certificate of Occupancy processing after required approvals are complete.
Inspections can be requested through the county’s e-Permitting system.
Schedule / manage inspections Residential inspection sequenceCertificate of Occupancy: What Happens at the End?
A Certificate of Occupancy is not simply issued because construction appears finished. Required building, trade, environmental and other applicable inspections must be completed first.
DeKalb County’s current permit page states that, once required inspections have been successfully completed, a CO may be obtained through DeKalb Development Services. The county instructs applicants to send a copy of the front and back of the permit to Developinspections@dekalbcountyga.gov.
For new homes and large additions, an as-built survey and other final land-development documents may also need to be completed before the permit card is submitted for the CO.
How to Check Permit Status or Find an Existing Permit
If you already applied, do not start another application just because the review is taking time. Start with your existing record number.
- Open the e-Permitting portal.
- Sign in with the account used for the application when applicable.
- Open the existing permit or application record.
- Review current status, outstanding fees, inspection information or available actions.
- If plans are under review, use the ProjectDox status tools linked from the county permit page.
- If you cannot identify the correct record, call 404-371-2155, option 3, with the property address and any permit/application number you have.
DeKalb GIS also directs residents to the county’s permit-tracking and e-Permitting tools for building, zoning and code-enforcement application updates.
Zoning, Land Development and Building Permits Are Different Reviews
One approval does not automatically replace another. A project can satisfy structural building rules but still conflict with zoning setbacks, a stream buffer, floodplain requirements, tree rules or land-development standards.
For land-development questions, DeKalb publishes Land Development guidance. For zoning questions, use the county’s Zoning Division page.
Construction Hours in DeKalb County
DeKalb County Code limits normal construction activity and deliveries to:
- Monday–Friday: 7:00 a.m.–7:00 p.m.
- Saturday: 8:00 a.m.–5:00 p.m.
- Sunday: no normal construction activity or deliveries.
The county code also identifies New Year’s Day, Thanksgiving Day, Christmas Day, Memorial Day, July 4 and Labor Day as restricted days, except for emergency activity needed to prevent harm or loss.
Common Mistakes That Slow Down a DeKalb Permit
- Applying to DeKalb County when the property is actually inside an incorporated city.
- Submitting a building application before checking zoning and site restrictions.
- Uploading plans without all required supporting forms.
- Using an outdated code edition for a new 2026 application.
- Starting permit-required construction before the permit is issued.
- Covering electrical, plumbing, HVAC, framing or other work before the required inspection.
- Assuming a building permit also clears zoning, health, fire, watershed or land-development requirements.
- Ignoring review comments instead of resubmitting the corrected documents through the existing record.
- Requesting a final inspection before trade and environmental approvals are complete.
DeKalb County Building Department FAQs
1. Where is the DeKalb County Building Department located?
The current Permits, Plan Review & Inspections office is at 178 Sams Street, Decatur, GA 30030. Call 404-371-2155 and select option 3 for permit information.
2. Can I apply for a DeKalb County building permit online?
Yes. DeKalb County provides an e-Permitting portal for permit services. Projects requiring plan review may also use ProjectDox through links provided on the county’s official permit page.
3. How do I know if DeKalb County or a city handles my permit?
Check the actual property jurisdiction before applying. Properties inside incorporated DeKalb cities are generally permitted by the city. Use the county’s official jurisdiction map rather than relying only on the mailing address.
4. Do small home repairs require a building permit?
DeKalb County Code contains an exception for ordinary repairs to a single-family residential building when wholesale cost does not exceed $3,000. This does not exempt every project below $3,000, especially structural or regulated trade work.
5. How much is a DeKalb County building permit?
The current 2026 fee schedule lists a $175 minimum building permit fee plus a $20 technology fee. New-construction fees are calculated from ICC valuation data, and other project-specific charges can apply.
6. How do I schedule a DeKalb County building inspection?
Use the DeKalb e-Permitting portal and open the issued permit record. Request the required inspection before the relevant work is concealed, and keep approved plans and the permit card at the site.
7. What inspections are required for a new home?
The sequence can include environmental, footing/foundation, in-slab, slab, damp-proofing, pre-cladding, electrical/plumbing/HVAC roughs, framing/insulation, grading, trade finals, environmental final and final building inspection.
8. What building code does DeKalb County use in 2026?
New 2026 projects generally use Georgia’s 2024 IBC/IRC code family with Georgia amendments, together with the applicable plumbing, mechanical, fuel-gas, fire, pool, electrical and energy codes. DeKalb published transition rules for applications started before the 2026 change.
9. Can a homeowner pull their own permit in DeKalb County?
DeKalb provides a Homeowner’s Affidavit for eligible owners taking responsibility for work on their primary residence. The affidavit and project requirements still have to be satisfied, and regulated trade work may have separate licensing requirements.
10. How do I get a Certificate of Occupancy in DeKalb County?
Complete all required inspections and final approvals first. DeKalb’s current instructions state that a copy of the front and back of the completed permit should be emailed to Developinspections@dekalbcountyga.gov for the applicable CO process.
Before You Submit
- Confirm the property is in DeKalb County permitting jurisdiction.
- Check zoning, setbacks and site restrictions.
- Select the correct permit type.
- Gather the complete application, plans and supporting approvals.
- Use DeKalb’s official e-Permitting system.
- Save your application number and answer review comments through the same project record.
- Do not begin permit-required work until authorization is issued.
- Request inspections before covering the work.
- Finish all trade, environmental and building finals before requesting the CO.
Nearby jurisdictions do not necessarily use the same portal, fees or application rules. For example, properties under City of Atlanta jurisdiction follow a different process, while counties such as Cherokee use their own local permit system. You can compare the Atlanta permit process or the Cherokee County building permit process when researching another Georgia property.
You can also browse additional local building department guides on USBuilding.org.
Information reviewed: October 24, 2026. USBuilding.org is an independent informational resource and is not affiliated with DeKalb County or the State of Georgia. Permit requirements can depend on the exact property, scope and existing approvals. Official county and state requirements control.