East Hampton Village, New York · 2026 permit guide
East Hampton Village Building Permits, Inspections & Local Requirements
If your property is actually inside the incorporated Village of East Hampton, building permits, plan review, construction inspections and certificates of occupancy are handled through the Village of East Hampton Building Department at 88 Newtown Lane, East Hampton, NY 11937.
When Do You Need an East Hampton Village Building Permit?
Village Code §104-5 says a building permit is generally required before the erection, construction, enlargement, alteration, removal, improvement, demolition, conversion or change in occupancy of a building or structure.
The important exception is ordinary repair work that is not structural and is not otherwise required to be permitted under the New York State Uniform Code. If your project sits in a gray area, describe the exact work to the Building Department before starting rather than assuming it is exempt.
| Project | What to expect |
|---|---|
| New house or major addition | Building permit, stamped plans, survey, zoning review, energy-code documents and other applicable approvals. |
| Structural remodeling | Building permit is normally required when walls, framing, structural components or the approved configuration are altered. |
| Swimming pool or spa | Detailed site and structural information is required. Pool contractors must meet Suffolk County certification requirements. |
| Demolition | A separate demolition permit is required. |
| New or altered driveway | A Department of Public Works road-opening permit is required before the building permit can be issued. |
| Work in a historic district | Design Review Board or historic approval may be required before the building-permit application is submitted. |
| Work affecting wetlands, dunes or coastal areas | Additional setbacks, flagging, coastal approvals or environmental documentation may apply. |
| Minor nonstructural repair | May fall under the ordinary-repair exception, but confirm if plumbing, electrical, structural, zoning or state-code requirements are involved. |
Official code reference: Village of East Hampton Code.
How to Apply for an East Hampton Village Building Permit
The fastest route is to prepare the complete package before you submit it. East Hampton’s own application checklist is unusually detailed, so using it as your working checklist can save a lot of back-and-forth.
- Confirm that the property is inside East Hampton Village. Do this before using any Town permit portal or Town application.
- Open the official Village Building Department page. Go to easthamptonvillage.gov → Building Department and locate the current forms and documents for your project.
- Read the Village’s building-permit requirements. Use the official Building Permit Application Requirements PDF before your architect, contractor or owner assembles the filing.
- Prepare the application and ownership documents. Complete the permit application and provide owner authorization if the person filing is not the property owner. LLC, trust or corporate ownership may require documentation showing who is authorized to approve the application.
- Collect contractor and insurance information. The Village checklist calls for contractor information and current insurance documents. Owners performing their own work may need the applicable CE-200 exemption documentation plus homeowners insurance.
- Prepare the plans and survey. The Village currently calls for two sets of signed and stamped plans from a New York State licensed architect or engineer for applicable projects, along with current survey information.
- Add outside approvals before filing where required. Depending on the property, this can include Suffolk County Health Department approval, wetlands or coastal approvals, DEC requirements, zoning relief, Design Review approval, demolition approval or stormwater documentation.
- Submit the complete package and required fee. Follow the current submission instructions shown by the Building Department. Call 631-324-4150 if you need the department to confirm a fee or project-specific requirement before filing.
- Wait until the permit is actually issued. An application is not permission to begin construction. The Village requires the issued permit placard to be posted so it is readily visible from the street before regulated work starts.
- Keep the approved plans at the job site. The current approved permit application and plans must be available to the inspector during scheduled inspections.
Documents You Should Have Ready
Not every small project needs every document below, but the Village’s current application requirements identify these as common items for building-permit filings.
- Completed Village building-permit application.
- Property owner information.
- Owner’s authorization when someone else is filing.
- LLC, corporation or trust authorization documents where applicable.
- Filed deed if ownership recently changed.
- General contractor and subcontractor information.
- Required contractor licenses or registrations.
- Current general liability, workers’ compensation and disability documentation where applicable.
- CE-200 exemption documentation for qualifying owner-performed work.
- Estimated construction cost.
- Two sets of signed and stamped architectural/engineering plans when required.
- Proposed Gross Floor Area Certification.
- Energy-code documentation such as applicable Manual J, D and S calculations and the selected compliance path.
- Two current surveys, generally dated within one year of application.
- Suffolk County Health Department approval where applicable.
- Required zoning, historic, environmental, coastal, stormwater or demolition approvals.
East Hampton Village Building Permit Fees
The Village’s currently published Building Department fee sheet is dated January 1, 2025. No newer Village building fee sheet was identified during this 2026 review, so confirm the amount with the department before submitting payment.
| Permit or service | Published amount |
|---|---|
| Building permit | 1.25% of estimated job cost |
| Certificate of Occupancy | $600 |
| Demolition permit | $1,000 |
| Coastal Erosion Management application | $750 |
| SWPPP fee | $2,000 |
| Wetlands flagging | Published sheet lists $725 up to 1.5 acres, increasing with acreage; call for current calculation. |
| Six-month permit renewal | Published at 0.75% of construction cost. |
| One-year renewal | Village fee sheet states the permit may be renewed for one year at the applicable original-fee rate for work completed to date. |
See the official Village Building Department fee schedule.
The same code provides an important accessibility exception: building-permit fees are waived for modifications to existing buildings made to improve access for persons with mobility impairments, including ramps and bathroom renovations covered by that provision.
East Hampton-Specific Requirements That Can Hold Up a Permit
1. Village street trees
If a Village street tree is affected by the construction site, the Building Inspector can require a protected area around the tree before the permit is issued. Village Code Enforcement inspects the protection before permit issuance, and the owner or builder must maintain it during construction.
See the official East Hampton Village Tree Protection Guidelines.
2. Driveways and road openings
For a new driveway or an alteration to an existing driveway, the Village permit instructions require a road-opening permit from the Department of Public Works before the Building Department issues the building permit. The Certificate of Occupancy is also held until the driveway meets the road-opening requirements and receives DPW sign-off.
3. Historic districts and Design Review
Projects within a historic district, or projects otherwise subject to Design Review Board review under Village rules, can require that approval before the building-permit application is submitted. This is especially important for exterior alterations, new structures and visually significant work.
4. Wetlands, dunes and coastal properties
A coastal or wetland lot can need much more information than an inland project. The Village’s survey checklist calls for applicable wetland flagging and setbacks, dune information and flood-zone data. Do not design the project to a generic setback and assume the Village will accept it.
5. Pools
For a proposed pool, the Village asks the survey to show items such as electrical service, the pool drywell, equipment and enclosure location, and required pool barriers. The structural plans must also address pool construction and drainage requirements.
6. Contractor registration
The Village permit instructions state that contractors, subcontractors, home-improvement contractors, electricians and plumbers already regulated by Suffolk County or the Town must also comply with the Village’s annual Contractor Registry requirement where applicable. Have this sorted out before the permit package reaches review.
How East Hampton Village Building Inspections Work
After the permit is approved, the Village attaches the required inspection sequence to the permit. The permit holder—not the inspector—is responsible for making sure those inspections happen.
- Read the inspection list attached to the issued building permit.
- Keep the approved plans and permit application at the property.
- Complete only enough work to reach the next inspection stage.
- Do not cover work that still needs inspection.
- Request the inspection from the Building Department by the method shown on the permit; Village guidance says inspection requests can be made by phone or email.
- Make the required area accessible and have approved plans available.
- Correct any items identified by the inspector.
- Request the next inspection or reinspection as required.
Final Inspection and Certificate of Occupancy
East Hampton Village has a detailed closeout process. Finishing the physical construction does not automatically close the permit.
The Village’s current permit instructions identify the following documents as potentially required before the final inspection, depending on the project:
- Final survey.
- Suffolk County Health Department final approval survey or “green stamp.”
- Electrical Certificate from an approved electrical inspection agency.
- Solder and anti-scald certificate.
- Gas supply-line installation certificate.
- HERS Certificate or applicable Energy Efficiency Certificate.
- Blower-door or duct-leakage certificate.
- Gross Floor Area “as-built” certification.
- Smoke/CO alarm affidavit.
- Final Cost Affidavit and additional fee if applicable.
- SWPPP termination letter from the DEC when applicable.
- Flood Elevation Certificate where required.
- Applicable covenants for a new Accessory Dwelling Unit.
- Fire-alarm registration and Knox Box requirements where applicable.
Village Code also states that a building or structure on which permit-required alteration work was performed cannot continue to be occupied for more than 30 days after completion unless the required Certificate of Occupancy has been issued.
For an existing-property CO matter, the Village also publishes a Certificate of Occupancy re-issuance application. Use the Building Department to confirm whether re-issuance or a project-specific CO application is appropriate for your situation.
One small detail that can stop a CO
Village Code requires the official building address number to be visibly displayed before a Certificate of Occupancy is issued. The numbers must be durable, at least four inches high and visible from the street. If the building sits too far back, the number may need to be displayed at the parcel frontage.
East Hampton Village Construction Hours in 2026
East Hampton Village has seasonal construction-hour restrictions. These are Village rules and should not be confused with the Town of East Hampton’s separate noise regulations.
| Period | Monday-Friday | Saturday | Sunday & federal holidays |
|---|---|---|---|
| January 1-May 14 | 8:00 AM-6:00 PM | 10:00 AM-6:00 PM | Prohibited |
| May 15-September 15 | 8:00 AM-6:00 PM | 12:00 PM-4:00 PM | Prohibited |
| September 16-December 31 | 8:00 AM-6:00 PM | 10:00 AM-6:00 PM | Prohibited |
The restrictions cover excavation, demolition, construction, exterior repair and alteration work covered by Village Code Chapter 196. A hardship permit may be requested from the Village Building Inspector for work outside the normal dates or hours when the inspector determines sufficient hardship exists.
Check the current rule directly in East Hampton Village Code Chapter 196 before scheduling crews.
Which Building Code Applies in 2026?
New York State’s 2025 Uniform Code and 2025 Energy Conservation Construction Code became effective December 31, 2025. New building-permit applications filed in 2026 therefore generally need to comply with the 2025 New York State code framework along with East Hampton Village zoning, local laws and project-specific approvals.
The State code set includes the 2025 Residential, Building, Existing Building, Plumbing, Mechanical, Fuel Gas, Fire and Property Maintenance Codes, together with the 2025 Energy Conservation Construction Code.
There is one important 2026 state-level caveat: New York’s Department of State says implementation and enforcement of certain 2025 provisions prohibiting fossil-fuel equipment and building systems in new buildings remain suspended by court order. This does not suspend the rest of the 2025 code.
Official state source: New York Department of State – 2025 Code Notice of Adoption.
How Long Is an East Hampton Village Building Permit Valid?
Village Code states that a building permit is generally valid for one year from issuance. The Code Enforcement Officer may allow up to three extensions, each for no more than one year, for good cause.
The Village’s published fee sheet also gives a six-month renewal option at 0.75% of construction cost. Do not wait until the last week of the permit to think about renewal. If construction or final paperwork will not be finished before expiration, contact the Building Department while the permit is still active.
Checking an Existing Permit or Property File
If you are buying a house, refinancing, planning a renovation or trying to solve an old open permit, start with the Village Building Department rather than assuming the Town’s OpenGov system contains the Village file.
- Have the exact property address ready.
- Record the Suffolk County tax-map number if you have it.
- Call the Village Building Department at 631-324-4150.
- Ask whether the property shows open building permits, missing inspections, violations or an existing Certificate of Occupancy.
- Ask what procedure is required to review or obtain copies of the property file.
- If older work does not match the Village record, ask what legalization, permit or updated documentation is required before taking action.
A Practical Path for Homeowners
If you just want to get a project moving without becoming a permit expert, use this order:
- Confirm Village jurisdiction.
- Write down the exact work you want to do.
- Check whether zoning, historic, wetlands, coastal, driveway or health approvals apply.
- Have your architect or engineer design around those restrictions before finalizing plans.
- Collect the current survey, contractor information and insurance at the same time.
- Use the Village permit-requirements checklist before submitting.
- Get the issued permit and post it before construction begins.
- Follow the inspection sequence printed on the permit.
- Start collecting closeout certificates before the project reaches the final inspection.
- Obtain the Certificate of Occupancy and keep a copy with your property records.
This may feel like extra preparation at the beginning, but it is usually much easier than discovering near the end that a survey, electrical certificate, road-opening sign-off or historic approval is missing.
Related New York Building Permit Guides
Jurisdiction is a common source of permit mistakes in New York. For comparison, see our Bronxville Building Department guide. If your question involves who issues permits when there is no single countywide building office, our Cattaraugus County building permit guide explains that distinction.
East Hampton Village Building Department FAQs
1. What is the East Hampton Village Building Department phone number?
The main Village number used by the Building Department is 631-324-4150. The Building Department is located at 88 Newtown Lane, East Hampton, NY 11937.
2. Is East Hampton Village Building Department the same as East Hampton Town Building Department?
No. They are separate governments with separate permit processes. A property inside the incorporated Village of East Hampton normally uses the Village Building Department. Do not file through the Town system until you have confirmed the property’s jurisdiction.
3. Do I need a building permit for renovations in East Hampton Village?
A permit is generally required for construction, enlargement, alteration, improvement, demolition, conversion and changes in occupancy. Ordinary nonstructural repairs may be exempt, but work involving structural, electrical, plumbing, zoning or other regulated components should be confirmed with the Village before work starts.
4. How much is an East Hampton Village building permit?
The currently published Village fee schedule lists the basic building-permit fee at 1.25% of the estimated construction cost, with a separate $600 Certificate of Occupancy fee. Confirm the current amount before payment because the published schedule can be changed by Village resolution.
5. How long is an East Hampton Village building permit valid?
Village Code provides a one-year permit period. Up to three extensions of no more than one year each may be allowed for good cause at the discretion of the Code Enforcement Officer. Renewal fees apply.
6. How do I schedule a building inspection in East Hampton Village?
Review the inspection requirements attached to the issued permit and contact the Village Building Department using the scheduling method provided. Village permit guidance states that inspection requests can be made by phone or email and that reasonable advance notice is required.
7. What paperwork is needed for the final inspection?
Depending on the project, the closeout package can include a final survey, Health Department approval, electrical certificate, energy certificates, blower-door or duct-leakage documentation, as-built gross-floor-area certification, smoke/CO affidavit, Final Cost Affidavit, flood certificate and other project-specific approvals.
8. What are the construction hours in East Hampton Village?
Monday-Friday hours are 8 AM-6 PM throughout the year. Saturday hours are normally 10 AM-6 PM except from May 15 through September 15, when Saturday work is limited to noon-4 PM. Construction is prohibited on Sundays and federal holidays under the current Village noise code.
9. Does work in an East Hampton Village historic district need extra approval?
It can. The Village’s permit requirements state that work within a historic district or otherwise subject to Design Review Board review may require approval before the building-permit application is submitted.
10. What happens if construction starts without the required Village permit?
Village Code allows the building-permit fee to be increased by 100% when permit-required work begins before the permit is issued. Unapproved work may also lead to enforcement or a stop-work order, so confirm permit requirements before demolition or construction starts.
Official East Hampton Village Resources
Information reviewed for 2026. Permit forms, fees, staff assignments and submission procedures can change. Use the Village’s official Building Department for the final application, fee confirmation, inspection scheduling and project-specific determination.