Building permits and inspections in Austin
The City of Austin Development Services Department handles building permit reviews, construction inspections, and related development services. Homeowners and contractors can use the City’s Austin Build + Connect (AB+C) portal to search permits, pay fees, and schedule inspections. Some applications must be submitted using separate official web forms.
Start here: Check your property’s jurisdiction and permit requirements, choose the correct application, then use the official City system to manage your project.
Office hours and service availability can differ. The PDC offers walk-ins for selected services; verify before visiting. Parking fees may apply for garage visits longer than 30 minutes.
Which building permits does Austin issue?
Austin Development Services reviews residential and commercial construction, alterations, and trade work. The required permit depends on the property, construction scope, zoning, and applicable building codes.
| Project type | Typical permit route |
|---|---|
| New house, addition, or accessory dwelling unit (ADU) | Residential Building Plan Review |
| Interior home remodel or garage conversion | Residential Plan Review or an eligible Express Permit |
| Fence, pool, uncovered deck, or demolition | Applicable residential project application; verify exemptions |
| Commercial construction, tenant finish-out, or change of use | Commercial Building Plan Review |
| Electrical, plumbing, and HVAC work | Related trade permits, often through AB+C or Building and Trade Contractor Services |
| Site development, signage, or right-of-way work | Separate City applications or partner department review may apply |
For the correct submission channel, use the City’s Types of Permits directory. Not all applications are accepted directly through AB+C.
Do you need a building permit?
Many structural changes, new buildings, additions, demolitions, and regulated trade installations require permits. Austin also exempts certain minor projects when they meet specific conditions.
| Residential work | Austin’s published exemption guidance |
|---|---|
| Painting, carpeting, cabinets, countertops | Generally exempt as ordinary finish work. |
| Detached storage shed | May be exempt if one story, 200 sq. ft. or less, 15 ft. or less in height, without plumbing or dwelling use, and outside a flood hazard area. |
| Residential fence | A fence no higher than 7 ft. may be exempt outside flood hazard areas, subject to applicable fence rules. |
| Uncovered deck | May be exempt if no more than 200 sq. ft., no more than 30 inches above grade, unattached to the home, not serving as required egress, and outside flood hazard areas. |
| New addition or substantial remodel | Generally requires a building permit and applicable reviews. |
Check your project: Open the City’s Do I Need a Permit? tool, answer the project questions, and review the recommended next step. The interactive guide normally takes about five minutes.
How to apply for a building permit in Austin
The following process covers the main residential permitting workflow. Commercial projects and specialized permits may require different applications and additional agency reviews.
- Confirm your property’s jurisdiction and permit requirements. Check your address, zoning, and applicable restrictions through the Property Profile and the City’s permit-requirement guide.
- Choose the correct application. Visit Residential Plan Review for home construction or Commercial Plan Review for commercial or qualifying multifamily projects.
- Prepare the required documents. Gather the applicable application form, property information, construction plans, plot plan or survey, elevations, and any required trade or supporting documents. The exact package depends on the project. Use the City’s published checklists.
- Submit the application using the authorized method. Follow the web form or portal instructions shown on the relevant City service page. Create an AB+C account to manage applicable permits, invoices, and inspections.
- Complete plan review and activate the approved permit. Pay review invoices, address any Master Comment Report corrections, and wait for approval. An authorized registered contractor or eligible homeowner must pay and activate the approved permit before regulated construction begins.
- Schedule required construction inspections. After the permit is Active, use AB+C’s “My Inspections” section to request the applicable inspection. Keep approved plans and required documents available at the job site.
- Complete final inspections and close out the project. Correct outstanding deficiencies, obtain final approvals, and secure a Certificate of Occupancy or Completion when applicable.
How to check Austin permit status and records
The AB+C Public Search function allows anyone to look up permits and development cases without creating an account.
For a step-by-step records walkthrough, see our Austin building permit search guide. Before preparing plans, review our guide to Austin building codes and local amendments.
- Open the official AB+C Portal.
- Select Public Search.
- Search using your permit or plan-review number, or use the property-search fields and the appropriate date range.
- Open the matching permit or case to review available status, history, inspections, and related documents.
- For an approved plan set, check the applicable record’s Folder Attachment area where available.
Common statuses include applications under review, requests for corrections, approved permits pending activation, Active permits, and completed or expired records. Exact labels vary by case.
If older files or approved drawings are unavailable online, use the City’s Records and Research service. Some archived records require a public information request and retrieval charges.
Austin building inspections: Scheduling and requirements
Austin inspectors check construction at required stages, including applicable foundation, framing, electrical, plumbing, mechanical, and final inspections. The inspection sequence depends on the approved project.
Schedule online through AB+C
- Log in to the AB+C Portal using an account linked to the permit.
- Verify the permit has Active status and all necessary fees have been paid.
- Open My Inspections and find the permit.
- Select the checkbox next to the permit and choose the required inspection.
- Click Schedule Inspection, select an available date, enter relevant access comments, and submit.
Schedule by telephone
To use the City’s automated IVR inspection line, first obtain an IVR PIN by completing the City’s Inspection Agent Letter of Authorization and Request for IVR PIN Number and emailing it to building.inspections@austintexas.gov. Then call 512-974-9405 with your PIN, 10-digit permit number, and 3-digit inspection code.
Official instructions: Schedule a Building Inspection.
- Complete the work being inspected and correct previous deficiencies.
- Display the property address clearly from the street.
- Make the construction area accessible and supply gate or entry instructions.
- Keep the latest City-approved plan set available for review.
- Upload supporting documents required for the specific inspection.
- Finish prerequisite trade inspections before requesting final approval.
Inspection timing: Austin reports that inspections are usually performed about 24 hours after scheduling, but workload can extend this to the next business day or approximately 48 hours. These are not guaranteed appointment times.
For inspection problems, cancellations, or emergency-inspection questions, contact building.inspections@austintexas.gov. The City publishes separate instructions for emergency repairs and one-time inspections.
2026 permit fees and processing times
Austin’s FY 2026–27 Development Services fee schedules became effective October 1, 2026. The amount payable depends on project type, size, review disciplines, permit requirements, and related inspections.
- Residential Building Plan Review and Permit Fees (PDF) ↗Residential application, review, and permit charges.
- Commercial Building Plan Review and Permit Fees (PDF) ↗Commercial construction and review charges.
- All Current Development Services Fee Schedules ↗Includes expedited reviews, site plans, historic preservation, and other services.
Payment detail: As published for FY 2026–27, AB+C credit card payments carry a 2.35% service fee ($2 minimum). Online checking-account payments are fee-free, although a $30 ACH return fee applies for insufficient funds. Other payment methods are available through City cashier services.
Published residential review timelines
| Application type | Published review timeframe |
|---|---|
| Express permit | Typically same day |
| Interior remodel | 5 business days |
| Fence | 5 business days |
| Residential demolition | 5 business days |
| Garage conversion or porch enclosure | 5 business days |
| Swimming pool or uncovered deck | 5 business days |
| New construction or addition | 10 business days |
| Update submittal | 7 business days |
These are the City’s published residential review timelines effective July 1, 2026—not guaranteed total permit issuance times. Review begins after an application is accepted and applicable invoices are paid. Corrections, additional review disciplines, or missing documents may extend the overall process. Commercial review times differ.
Austin building codes in effect in 2026
The City of Austin uses technical building codes adopted under Chapter 25-12, with local amendments. The following editions are listed in the City’s official adopted-code resources.
| Code | Applicable edition |
|---|---|
| International Residential Code (IRC) | 2024 |
| International Building Code (IBC) | 2024 |
| International Energy Conservation Code (IECC) | 2024 |
| International Existing Building Code (IEBC) | 2024 |
| International Fire Code (IFC) | 2024 |
| Uniform Mechanical Code (UMC) | 2024 |
| Uniform Plumbing Code (UPC) | 2024 |
| National Electrical Code (NEC) | 2026 — effective September 1, 2026 |
The listed 2024 technical-code amendments generally became effective July 10, 2025. Additional adopted codes cover swimming pools, property maintenance, and wildland-urban interface construction. Project approval may depend on applicable transition, vesting, and local amendment provisions.
Official reference: Austin Building Technical Codes and Local Amendments.
Local requirements that may affect your project
Before spending money on architectural plans or construction, check the location-specific conditions below.
- City limits versus ETJ: An Austin mailing address does not prove the property is inside Austin’s full municipal jurisdiction. Permitting authority differs by location; Austin also handles certain electrical and plumbing inspections in its extraterritorial jurisdiction.
- Zoning and land-use restrictions: Lot coverage, setbacks, permitted uses, height, and impervious-cover limitations may affect approval.
- Floodplain and drainage: Properties in mapped flood hazard areas may require additional review, even for work that would otherwise qualify for an exemption.
- Historic properties and trees: Protected trees, historic districts, and designated properties may trigger additional approvals.
- Right-of-way work: Driveway approaches, sidewalks, curb cuts, and related construction can require Transportation and Public Works review.
- Private deed restrictions: HOA rules or restrictive covenants may apply separately from City permitting approval.
Permit expiration and certificates of occupancy
An approved building permit must be activated before regulated work begins. Austin permits can expire after approximately 180 days without qualifying construction inspection activity. Review the expiration date and extension rules on your permit record; a canceled inspection or an unsuccessful no-work inspection may not preserve permit validity.
When a permit expires, the responsible contractor or property owner may need to request an extension or reactivation through the AB+C Portal or the City’s Modify a Permit process.
After the required final inspections, eligible projects receive a Certificate of Occupancy (CO) or other applicable completion approval. Existing CO copies can be requested by emailing DSDCertificateofOccupancy@austintexas.gov with the property address and unit number. For requests of up to six certificates, the City lists a typical response period of 1–5 business days.
See the City’s Certificate of Occupancy guidance for new certificates, existing records, and temporary occupancy requests.
Official Austin permit resources
- Development Services Contact Information ↗Office address, assistance, and department contacts.
- Residential Building Plan Review ↗Residential applications, instructions, documents, and review timelines.
- Commercial Building Plan Review ↗Commercial construction and multifamily review requirements.
- Permit Forms and Applications ↗Government applications, supporting forms, and checklists.
- Inspection Scheduling Instructions ↗Online and IVR scheduling procedures.
- Permitting Center Appointments ↗In-person and virtual appointment options.
Frequently asked questions
1. Who issues building permits in Austin, Texas?
The City of Austin Development Services Department handles building permit reviews and construction inspections within its applicable jurisdiction. Properties outside city limits may fall under different permitting authorities.
2. Where is the Austin Building Department located?
Austin Development Services operates at the Permitting and Development Center, 6310 Wilhelmina Delco Drive, Austin, TX 78752. The building is open Monday through Friday, 7:45 a.m. to 4:45 p.m. Selected walk-in services operate from 8 a.m. to 4 p.m.
3. Do I need a permit to remodel my house or build a shed in Austin?
Structural remodels and additions generally require permits. Certain finish work is exempt. A one-story detached shed may qualify for an exemption if it is no larger than 200 square feet, no higher than 15 feet, has no plumbing or dwelling use, and is outside a flood hazard area. Other restrictions still apply.
4. Can I apply for an Austin building permit online?
Yes. Some permits are available through Austin Build + Connect (AB+C), while residential and commercial plan-review applications may require dedicated City web forms. Select the permit type on the official Development Services website to find the correct submission method.
5. How much does an Austin building permit cost in 2026?
Permit fees vary with project type, size, plan review, and required services. Austin’s FY 2026–27 fee schedules took effect October 1, 2026. AB+C credit card payments have a 2.35% service fee, with a $2 minimum. Check the applicable official fee schedule for your project.
6. How long does Austin building permit approval take?
Under the residential timelines effective July 1, 2026, interior remodel and demolition reviews are listed at 5 business days, while new construction and additions are listed at 10 business days. Express permits are typically reviewed the same day. Incomplete submissions, corrections, and additional reviews can increase the total time.
7. How do I check my Austin building permit status?
Open the AB+C Portal, select Public Search, and look up the permit using its number or property information. Public Search does not require an account and provides available permit, case, and inspection history.
8. How do I schedule a building inspection in Austin?
Log in to AB+C with an account linked to an Active permit, open My Inspections, select the permit and inspection, and request a date. You can also call 512-974-9405 using an assigned IVR PIN, your 10-digit permit number, and the 3-digit inspection code.
9. Can a homeowner obtain a permit without hiring a general contractor?
Eligible homeowners may act as their own general contractor under Austin’s homeowner permitting rules. They must meet the applicable registration and permit requirements and take responsibility for activating permits, coordinating trades, scheduling inspections, and obtaining final approvals.
10. Which building codes apply in Austin during 2026?
Austin lists the 2024 International Residential Code, International Building Code, and other 2024 technical codes with local amendments. The 2026 National Electrical Code became effective September 1, 2026. Verify the applicable edition and amendments for your specific project.
Information reviewed: October 8, 2026. This independent guide summarizes publicly available City of Austin information and is not affiliated with the City government. Confirm project-specific decisions, fees, inspection requirements, and code applicability with Austin Development Services before beginning work.