Fort Lauderdale Building Permits, Inspections & Official Services
Information reviewed for November 2026. Permit requirements, fees and staff assignments can change, so use the linked City resources when completing a live transaction.
First Check: Does the City of Fort Lauderdale Handle Your Property?
This is worth checking before you fill out a form or pay a fee. The City states that it processes permit applications only for addresses inside Fort Lauderdale’s municipal boundaries.
- Open the City’s Property Reporter. Use the official Fort Lauderdale Property Reporter GIS.
- Search the property. Enter the street address or parcel/folio information.
- Confirm the governmental boundary. Make sure the parcel is actually within the City of Fort Lauderdale rather than an unincorporated Broward area or another municipality.
- If it is outside the City, stop before submitting a City permit. Determine which municipality or Broward County office has jurisdiction.
What the Fort Lauderdale Building Services Division Handles
Building Services is part of Development Services. Its work includes permit intake, plan review, permit issuance, building-code compliance, construction inspections and access to permit/property records. Other DSD divisions may become involved when a project affects zoning, landscaping, site development or the public right-of-way.
| Project or need | What to expect |
|---|---|
| New house or commercial building | Master building permit, plans, trade permits, zoning/development review and staged inspections. |
| Addition or structural remodel | Building plan review plus electrical, plumbing or mechanical permits when those systems are affected. |
| Roof replacement | Roof permit, applicable product/assembly documentation and roofing inspections. |
| Windows, doors or shutters | Permit and applicable product approval/High-Velocity Hurricane Zone documentation. |
| Air-conditioning replacement | Mechanical permit unless a specific lawful exemption applies. |
| Electrical or plumbing work | Separate regulated trade permit and inspections as applicable. |
| Fence or driveway | Zoning review may apply; residential fences and paving are among the City’s listed Walk-Thru permit types. |
| Shed | Building permit required. The City also identifies HVHZ engineering/product-approval requirements. |
| Dock or seawall | City permits plus additional Broward County approval may be required. |
| Permit records/status | Search through LauderBuild without creating a new permit application. |
Official Permitting Services Official Forms & Checklists
Do You Need a Building Permit?
For most construction, alteration, repair, demolition and regulated electrical, gas, mechanical or plumbing work, assume a permit may be required until the City confirms otherwise. Do not begin regulated work simply because an online application has been created; the City instructs applicants to wait until the permit is issued.
Examples specifically addressed by the City’s permitting information include sheds, parking-lot seal/restripe work, docks, residential fences, driveways, re-roofing, window and door replacement, electrical service changes, A/C replacement, water heaters and sewer connections.
Important 2026 Change: HB 803 and the $7,500 Residential Exemption
Florida House Bill 803 took effect July 1, 2026, and Fort Lauderdale updated its permitting process. Certain cosmetic, non-structural work on a single-family residence valued at less than $7,500 may qualify for exemption from the building permit requirement.
| May qualify | Does not qualify under this exemption |
|---|---|
| Interior painting | Structural work |
| Flooring replacement | Electrical work |
| Cabinet replacement | Plumbing or gas work |
| Minor drywall repair/finishing | Mechanical/HVAC work |
| Other qualifying cosmetic work | Commercial, condo, apartment or multifamily work |
| Single-family property meeting all conditions | Property partially or entirely in a flood hazard area |
How to use the exemption correctly
- Confirm the property is a qualifying single-family residence.
- Obtain a project proposal or job-cost estimate showing the value is below $7,500.
- Open the City’s HB 803 permitting update.
- Complete the Residential Permit Exemption Request.
- Submit the request through LauderBuild.
- Wait for written City approval before beginning work.
The City also states that a larger project cannot be split into several smaller jobs simply to remain below the $7,500 threshold. Zoning, HOA or other rules can still apply even when a building permit exemption is approved.
How to Apply for a Fort Lauderdale Building Permit Online
Fort Lauderdale uses LauderBuild, its Accela Citizen Access system. New permit applications and related submissions are handled digitally.
- Confirm jurisdiction first. Use Property Reporter so you do not submit to the wrong government.
- Choose the correct permit type. Review the City’s forms and project checklists before opening the application.
- Create or sign in to LauderBuild. Open the official LauderBuild portal. Registration is free.
- Start the permit record. After signing in, use Apply → Permits/Engineering (ROW) and select the application that matches the work.
- Enter the property and project information. Have the address, folio number, owner information, contractor information, work description and job value ready.
- Pay required initial fees. Under the City’s 2026 HB 803 procedures, initial permitting fees are due with the application. Additional charges can be assessed during review.
- Upload plans and supporting documents in the LauderBuild Plan Room. Use the proper document category for each file.
- Monitor reviewer comments. Sign back in, locate the record and use the Plan Room to see review notes and correction requests.
- Upload only corrected sheets when requested. Do not automatically upload an entire replacement plan set when the City asks for selected revised sheets.
- Pay remaining fees and obtain the issued permit. Do not start regulated work until the permit is formally issued.
Documents to Prepare Before You Start the Application
The exact package varies by project, but preparing the common items below can prevent an avoidable correction cycle.
- Current Broward County Uniform Building Permit Application when required.
- Property address and tax folio/parcel number.
- Clear description and estimated value of the work.
- Owner and contractor information.
- Applicable contractor license and registration information.
- Current signed and sealed survey for exterior work.
- Site plan locating proposed exterior improvements.
- Architectural, structural or trade drawings when required.
- Product approvals or Miami-Dade NOAs where required for HVHZ-regulated components.
- Energy, flood, engineering or equipment documents applicable to the project.
- Owner-Builder Affidavit if using the lawful owner-builder path.
- Notice of Commencement when required.
- Private-provider documents if plan review or inspections will be performed under Florida Statute 553.791.
LauderBuild Plan Room file rules that commonly matter
- Professional plans and surveys that require professional certification must be digitally signed and sealed.
- Use PDF files and the document category that matches the file.
- Do not combine unrelated supporting documents into one file.
- Keep plan sheet numbers consistent through revisions.
- Reserve the City’s required approval-stamp area on applicable plan sheets.
- Plans must be legible and drawn to the required scale.
- Current LauderBuild online guidance states uploaded files must be under 250 MB.
- Do not alter a professionally digitally signed document after signing because doing so can invalidate the signature.
LauderBuild Guides & Plan Room Help
Fort Lauderdale Building Permit Fees in 2026
There is no single flat permit price. The City’s current DSD fee page links the active Permitting Fee Schedule, and charges depend on construction value, permit type, review disciplines, revisions, reinspections and other project-specific services.
| Selected fee item | Published basis / 2026 guidance |
|---|---|
| Master permit | Minimum $131 or 1.75% of construction cost under the published building fee structure. |
| Stand-alone permit | Minimum $131 or 1.75% of construction cost. |
| Trade permit | Minimum $131 or 1.75% of construction cost. |
| Permit renewal before expiration | 50% of the original permit fee under the City’s published renewal guidance. |
| Permit renewal after expiration | 100% of the original permit fee under the City’s published guidance. |
| Private Provider — inspection, project $25,000 or less | $105 base; qualifying commercial discount may apply. |
| Private Provider — plan review + inspection, $25,000 or less | $105 base; qualifying commercial discount may apply. |
| Private Provider — inspection, project $25,001+ | $273 base before applicable commercial discount. |
| Private Provider — plan review + inspection, project $25,001+ | $446 base before applicable commercial discount. |
Payment change for 2026: Fort Lauderdale’s HB 803 implementation states that initial permit fees are due when the application is submitted. Additional fees can be added during plan review, and remaining balances must be paid before final permit issuance.
Check Current DSD Fee Schedule
How to Search a Fort Lauderdale Permit or Check Status
You do not have to start a new application just to search records. Public users can use LauderBuild to search and view general record information.
- Open LauderBuild Permit Search.
- Search by record number, address or available property fields.
- For an address search, start broad. The portal recommends using only the street number and street name if a full-address search returns nothing.
- If necessary, use % as a wildcard in the street-name field.
- If searching a permit created before October 4, 2019, prefix the old permit number with PM-.
- Open the matching record to review status, fees, processing information or inspection history that is publicly available.
When searching by a full modern record number, include the letters and dashes exactly as shown on the application or permit.
How to Schedule a Fort Lauderdale Building Inspection
After the permit is issued and the work has reached the required inspection stage, inspections can be managed in LauderBuild.
- Open the permit record in LauderBuild.
- Choose the arrow beside Record Info.
- Select Inspections.
- Choose Schedule an Inspection.
- Select the required inspection type.
- Choose an available date and select the listed all-day option.
- Verify the property and contact information.
- Submit the request and later check the record for the result.
The City does not guarantee a specific arrival time. Make sure the work is accessible and do not conceal work that still requires inspection. For an after-hours inspection request, contact the chief inspector for the applicable discipline; additional fees may apply.
Fort Lauderdale also states that ADA inspection is now a separate inspection where applicable and must be passed before issuance of a Certificate of Occupancy or Certificate of Completion for structures that will be occupied.
Find Inspectors & Chief Inspectors
Notice of Commencement: What Fort Lauderdale Applicants Should Know
The City’s permitting FAQ states that a Notice of Commencement is required for qualifying construction contracts exceeding $5,000. The recorded document identifies the project, owner, contractor and other parties and must be handled according to Florida construction-lien law.
Because statutory thresholds and procedures can differ for certain work types, use the current Broward County Notice of Commencement instructions for the project rather than relying only on an old form.
Practical steps
- Complete the current Notice of Commencement with the correct legal property and project information.
- Record it with Broward County Records, Taxes and Treasury when required.
- Obtain the recorded/certified copy required for the permit.
- Provide the required record to the permitting authority.
- Post the required Notice of Commencement at the job site before the applicable inspection.
The City lists Broward County Governmental Center, Room 114, 115 S. Andrews Avenue, Fort Lauderdale, FL 33301 as one location where recording services are available.
Can a Fort Lauderdale Homeowner Pull Their Own Permit?
The City’s published guidance allows an owner of a one- or two-family dwelling to act as their own contractor when the legal owner-builder conditions are met. The home must be for the owner’s own use and not for sale or lease, and the owner must perform the work or provide the required direct on-site supervision.
The City requires an Owner/Builder Affidavit. Commercial property owners generally must use an appropriately licensed contractor for work requiring a building permit and inspection.
Before selecting owner-builder simply to save contractor cost, read the affidavit carefully. The owner takes on responsibilities normally handled by the contractor, including permitting, supervision, compliance and certain worker/lien obligations.
Permit Applications, Expiration and Renewal
Different clocks can apply depending on whether you are discussing an application, an issued permit or a special permit type.
| Situation | City guidance |
|---|---|
| Application not actively pursued | An application may be treated as abandoned 180 days after filing unless pursued in good faith or a permit has been issued. |
| Renewal before permit expiration | Published City guidance lists 50% of the original permit fee. |
| Renewal after expiration | Published City guidance lists 100% of the original permit fee. |
| Additional renewal | The City states a permit can generally be renewed once; further renewal is at the Building Official’s discretion. |
| Single-family permits affected by HB 803 | City guidance states they expire one year after issuance or on the effective date of the next Florida Building Code, whichever is later. |
| Voluntary demolition permit | The City’s 2026 announcement states a voluntary owner demolition permit is valid for 60 days. |
Fort Lauderdale Building Safety Inspection Program
This is different from the ordinary inspections performed during new construction. Broward’s Building Safety Inspection Program applies to qualifying older buildings in Fort Lauderdale.
- The initial inspection applies when a covered building reaches 25 years of age.
- Subsequent inspections are generally required every 10 years.
- The City sends notice to affected owners.
- Owners generally have 180 days after receiving notice to submit the required structural and electrical safety report.
- The inspection must be performed by an appropriately licensed engineer or registered architect.
- The City currently lists a $375 review fee.
- Reports are submitted electronically through the Building Safety Inspection Program application in the LauderBuild Plan Room.
Exemptions include certain small residential buildings, fee-simple townhouses, qualifying structures under 3,500 square feet and other categories identified by the program.
Official Building Safety Inspection Program
Which Building Code Applies in Fort Lauderdale in November 2026?
As of November 2, 2026, the effective statewide code is the Florida Building Code, 8th Edition (2023), which became effective December 31, 2023.
The 9th Edition (2026) Florida Building Code is scheduled to become effective December 31, 2026. If a project will be submitted or substantially revised near the end of December, confirm the governing code edition before finalizing plans.
Broward County is also within Florida’s High-Velocity Hurricane Zone (HVHZ). This is especially important for roofs, windows, exterior doors, shutters, structural connections and product approvals.
Florida Building Commission Fort Lauderdale Code Resources
When Broward County Approval Is Also Needed
A Fort Lauderdale City permit does not automatically satisfy every county-level approval. Some projects may need associated Broward County environmental, transportation, asbestos, Notice of Commencement or other approvals.
Broward County’s ePermits OneStop connects participating municipal permit applications with applicable county reviews. Use it when the City’s application or project checklist identifies a Broward County approval.
Common examples can include:
- Asbestos-related review for applicable projects.
- Transportation concurrency or environmental review.
- Notice of Commencement processing.
- County approvals connected to docks or other regulated work.
- Other agency clearances identified during municipal plan review.
Common Fort Lauderdale Permit Problems and the Practical Fix
| Problem | What to do |
|---|---|
| Address will not appear in LauderBuild | Enter less information. Try only the street number and street name, and first verify that the parcel is inside Fort Lauderdale. |
| Old permit cannot be found | For records created before October 4, 2019, try the permit number with the PM- prefix. |
| Application sits in review | Open the Plan Room and check reviewer comments, missing document requests and unpaid fees. |
| Digital plan is rejected | Check file category, naming, digital signature/seal, sheet numbering, scale and readability. |
| Inspection cannot be scheduled | Confirm the permit has been issued and that required prior inspections, fees and sub-permits are complete. |
| Inspection fails | Read the inspector’s comments, correct the cited work and request reinspection only after the correction is ready. |
| Project is outside City limits | Use the correct municipality or Broward County permitting authority instead of continuing in LauderBuild. |
| Permit is near expiration | Contact DSD before expiration and use the correct renewal process rather than continuing work under an expired permit. |
| Work was already done without a permit | Stop further concealed work and contact Building Services about the applicable after-the-fact procedure. |
| Permit is finished but still open | Check for missing final inspections, sub-permit finals, outstanding fees or required CO/CC closeout documents. |
Who to Contact for the Right Question
| Need | Contact |
|---|---|
| General City/DSD assistance | 954-828-8000 |
| Permit problem-solving assistance | Permit Solutions Team · 954-828-3160 · PermitSolutions@fortlauderdale.gov |
| Inspection scheduling assistance | 954-828-6520, Option 1 |
| Building Official | John Travers · 954-828-5913 · JTravers@fortlauderdale.gov |
| Certificate of Occupancy questions | COinquiries@fortlauderdale.gov |
| LauderBuild assistance | LauderBuild@fortlauderdale.gov |
| Planning | Planning@fortlauderdale.gov · 954-828-6520 |
For a discipline-specific inspection question, the City publishes direct contacts for building, electrical, mechanical, plumbing, flood and other inspection staff on its DSD Contact Information page.
Fort Lauderdale Building Department FAQs
1. Where is the Fort Lauderdale Building Department located?
Building permitting services are part of the City of Fort Lauderdale Development Services Department at the Greg Brewton Center, 700 NW 19th Avenue, Fort Lauderdale, FL 33311. The department lists regular hours of Monday through Friday, 8:00 a.m. to 4:00 p.m.
2. How do I apply for a Fort Lauderdale building permit?
Use the City’s LauderBuild portal. Create or sign in to an account, select Apply and then Permits/Engineering (ROW), choose the correct permit type, complete the record, pay applicable initial fees, and upload the required plans and supporting documents through the LauderBuild Plan Room.
3. Can I search Fort Lauderdale permits without creating an account?
Yes. The City allows public users to search and view general record information in LauderBuild without registering. An account is needed for additional services such as submitting applications and managing project records.
4. How do I schedule a Fort Lauderdale building inspection?
Open the permit in LauderBuild, select Record Info, choose Inspections, select Schedule an Inspection, choose the inspection type and an available date, verify the contact information and submit the request. Inspection assistance is also available at 954-828-6520, Option 1.
5. What time do Fort Lauderdale inspectors normally perform inspections?
The City states that inspections are generally conducted between 8:00 a.m. and 3:30 p.m. A specific arrival time is not guaranteed. For a timing accommodation, the City recommends contacting the assigned inspector between 7:30 and 8:00 a.m.
6. Does work under $7,500 automatically avoid a building permit in 2026?
No. The 2026 HB 803 exemption is limited to qualifying cosmetic, non-structural work on eligible single-family properties. Fort Lauderdale requires the owner or contractor to submit a Residential Permit Exemption Request and receive written approval before starting work.
7. Can I pull my own permit as a Fort Lauderdale homeowner?
A qualifying owner of a one- or two-family dwelling may use the owner-builder provision when the home is for the owner’s own use, is not for sale or lease, and the owner meets the supervision and legal requirements. The City requires an Owner/Builder Affidavit.
8. How much does a Fort Lauderdale building permit cost?
Permit cost depends on project value and permit type. The City’s published structure uses a minimum charge and valuation-based calculation for many building and trade permits. Initial fees are now collected with the application, and additional review-related charges can be added. Check the current DSD Fee Schedule before budgeting.
9. Which Florida Building Code applies in Fort Lauderdale in November 2026?
As of November 2, 2026, the Florida Building Code, 8th Edition (2023), remains the effective statewide edition. The 9th Edition (2026) is scheduled to take effect December 31, 2026. Broward County HVHZ requirements also matter for applicable work.
10. Does a Fort Lauderdale permit also cover Broward County approvals?
Not necessarily. A City building permit and Broward County associated approvals are different processes. Depending on the project, Broward ePermits OneStop may be used for county environmental, asbestos, transportation or other reviews connected to the municipal permit.
Before You Submit: Five Checks That Can Save a Rejection
- Confirm the property is actually inside Fort Lauderdale.
- Choose the permit that matches the real scope of work.
- Download the current City checklist and forms instead of reusing an old package.
- Prepare every required plan, survey, product approval and supporting document before sending the review package.
- Do not start regulated work until the permit or written exemption is approved.
For most users, the simplest route is: verify jurisdiction, prepare the correct documents, submit through LauderBuild, respond to plan-review comments, obtain the issued permit, schedule each required inspection and make sure the permit receives its final approval before considering the project complete.