Lee County, Florida • 2026 Permit Guide
Lee County Building Permits, Inspections & Official Services
If you are building, remodeling, replacing a roof, installing windows, adding a pool, changing electrical or plumbing systems, checking an old permit, or scheduling an inspection in unincorporated Lee County, the main agency is Lee County Community Development — Building & Permitting Services.
First Check: Does Lee County Actually Issue Your Permit?
This is the most important first step. Lee County Community Development handles permitting primarily for unincorporated Lee County. A Fort Myers, Bonita Springs or Cape Coral mailing address does not automatically mean Lee County is the correct permitting authority.
| Property location | Where to start |
|---|---|
| Unincorporated Lee County | Lee County Community Development / eConnect |
| City of Bonita Springs | Use the City permitting system. See our Bonita Springs Building Department guide. |
| City of Cape Coral | Use Cape Coral Development Services. See our Cape Coral Building Department guide. |
| City of Fort Myers | City of Fort Myers Building, Permitting & Inspections |
| Village of Estero | Confirm permitting responsibility with the Village before applying |
| Town of Fort Myers Beach | Town building/permitting services |
| City of Sanibel | City of Sanibel permitting authority |
How to confirm the jurisdiction in two minutes
- Open the official LeeGIS Property Information tool.
- Search the street address or STRAP/parcel number.
- Review the municipality and district information for the parcel.
- If the property is inside an incorporated municipality, confirm that city’s permit process before paying fees or submitting plans.
This simple check can prevent an application from being submitted to the wrong government agency.
Lee County Building Department Contact Information
| Service | 2026 information |
|---|---|
| Official department | Lee County Department of Community Development — Building & Permitting Services |
| Office | 1500 Monroe Street, Fort Myers, FL 33901 |
| Community Development | 239-533-8585 |
| Permitting | 239-533-8329 |
| Plan Review | 239-533-8597 |
| Building Inspections | 239-533-5801 |
| Contractor Licensing | 239-533-8119 |
| Floodplain Management | 239-533-8948 |
| Permitting lobby | Monday-Friday, 9:00 a.m.-4:00 p.m., excluding County holidays |
| Inspection phone hours | Monday-Friday, 7:00 a.m.-4:00 p.m. |
| Online system | Lee County eConnect / Accela Citizen Access |
What Work Usually Needs a Lee County Building Permit?
Lee County states that permits are generally required to construct, enlarge, alter, repair, move or demolish a building, change its occupancy, or install or modify regulated electrical, gas, mechanical or plumbing systems.
Some work may be exempt under the Florida Building Code, Lee County Land Development Code or newer Florida law. Do not decide that a project is permit-free based only on its cost or size.
Important 2026 Florida Permit Changes
Qualifying work under $7,500
Florida Statute 553.79 now requires local governments to exempt qualifying work valued at less than $7,500 on a single-family dwelling property from the building-permit requirement.
However, the exemption does not apply when:
- the property is partly or entirely in a Florida Building Code flood hazard area;
- the work is electrical;
- the work is plumbing;
- the work is structural;
- the work is mechanical; or
- the work involves gas.
The project also cannot be divided into smaller jobs just to avoid permitting. To use the exemption, the owner or contractor must submit a written exemption request to the local enforcement agency with documentation showing the nature and value of the work.
Practical advice: do not simply start a $5,000 project because it is below $7,500. First check the property’s flood status, identify whether any regulated trade or structural work is involved, and ask Lee County whether the written exemption process applies.
Faster review for some projects below $15,000
Florida’s 2026 permit-processing law also sets a 5-business-day decision timeframe for certain complete and sufficient permit applications involving an existing single-family dwelling when the work is valued below $15,000 and the applicant uses local-government plan review.
This does not mean every application is automatically issued within five days. Missing documents, incomplete applications, code corrections and applicant-caused delays can affect the process.
Which Florida Building Code applies in November 2026?
Lee County currently identifies the Florida Building Code, 8th Edition (2023) for building permit applications. The 9th Edition (2026) is scheduled to become effective on December 31, 2026.
For a statewide explanation, see our Florida Building Code 2026 guide.
How to Apply for a Lee County Building Permit Online
Lee County uses the eConnect Citizen Access system for online applications. The portal is also used for document uploads, permit tracking, payments and inspections.
- Confirm jurisdiction. Make sure the property is in the Lee County permitting jurisdiction rather than Bonita Springs, Cape Coral, Fort Myers, Estero, Fort Myers Beach or Sanibel.
- Open Lee County eConnect. Register or sign in if your transaction requires an account.
- Choose Permitting. Select the option to create or manage a permitting application.
- Select the correct record type. Choose the permit category that matches the actual project rather than picking a similar category just to get started.
- Enter the property. Search by address or parcel/STRAP information and verify that the correct parcel appears.
- Complete the project details. Provide the scope, valuation, contractor or owner-builder information and other requested fields.
- Upload required documents. Records using Digital Projects/DigEplan should use the document categories shown in the portal. Do not upload one file repeatedly under different categories.
- Monitor the record. Watch for intake comments, plan-review corrections, outstanding conditions and assessed fees.
- Pay the required fees. Payment does not replace outstanding reviews or conditions. Wait until the permit shows that it has been issued before starting regulated work.
How to Search a Lee County Permit Without Starting a New Application
You do not need to call the department just to perform a basic permit search. Public record searches are available through eConnect.
- Open the official Lee County permitting search.
- Choose the Permitting search area.
- Search by record number when you have it. This is normally the cleanest search.
- If you do not know the permit number, search by site address, parcel number, contractor information or other available criteria.
- When searching by street name, avoid adding unnecessary street-type abbreviations if they prevent a match.
- Open the matching record to review status, dates, inspection history and available record details.
If an old document is missing
Lee County has been migrating older permitting documents into its newer digital system. If a permit appears but its approved plans or documents are not visible, use the County’s document-request process rather than assuming the file no longer exists.
For records that require a formal public-record request, Lee County moved new requests to its NextRequest Public Records platform beginning May 1, 2026.
What Should You Prepare Before Applying?
The exact checklist depends on the project. Preparing the basics before opening the application can save a round of intake corrections.
- Property address
- Parcel or STRAP number
- Detailed scope of work
- Estimated construction value
- Contractor information
- Owner-builder documents when applicable
- Site or aerial plan
- Construction drawings
- Survey when required
- Florida Product Approval information
- Engineering documents when required
- Energy documentation when applicable
- Flood documentation when applicable
- Development or zoning approval when required
- Notice of Commencement when required
Notice of Commencement
Florida law requires a Notice of Commencement for many projects when the direct contract exceeds the statutory threshold. The recorded notice generally must be available before the first inspection when required.
Lee County provides a Notice of Commencement form through its Application & Information Center, while recording is handled through the Lee County Clerk of Court.
Lee County Building Permit Fees in 2026
Lee County adopted a revised Community Development building permit fee schedule effective April 15, 2026. There is no single flat permit price because the amount depends on record type, plan review, inspections, project size and other reviews.
| 2026 fee item | Published amount |
|---|---|
| Application fee | $50 per applicable application |
| Technology fee | $35 per application |
| Operational Support Fee | Percentage of applicable review and inspection fees |
| Additional / partial inspection | $50 |
| Re-inspection | $50 |
| Permit extension — 3 months | $50 |
| Contractor change | $50 |
| Work without permit | Double applicable review and inspection fees, $200 minimum |
| New residential building plan review | $75 initial; $25 resubmission |
| New residential regulatory review | $35 initial; $25 resubmission |
Inspection fees for larger projects may be calculated by square footage and trade. Roofing, structural, electrical, mechanical and plumbing fees can therefore differ substantially between projects.
Check the official 2026 Building Permit Fee Schedule before budgeting.
Impact fees, DOT permits, well permits and other agency charges are separate from the Community Development building-permit fee schedule.
How to Schedule a Lee County Building Inspection
After a permit is issued, the contractor or owner-builder is responsible for requesting the inspections required for the permitted scope of work.
- Open eConnect.
- Select the permitting inspection option.
- Locate the issued permit.
- Select the correct inspection type/code for the stage of work.
- Submit the inspection request and verify that it appears on the permit record.
- After the visit, return to the record and review the inspection result before covering work or moving to the next required stage.
Common Lee County inspection codes
| Trade | Examples |
|---|---|
| Structural | 101 Foundation/Footing, 105 Rough Framing, 106 Final Structural |
| Electrical | 303 Service Change, 304 Rough Electrical, 305 Electrical Final |
| Mechanical | 401 Rough A/C, 402 A/C Final |
| Plumbing | 201 First Rough, 202 Second Rough, 204 Final Plumbing |
| Roofing | 501 Roof Dry In, 502 Roof In Process, 503 Roof Final |
| Other | 117 Shed Final, 120 Fence Final, 121 Sign Final |
For fire inspections, Lee County describes a two-step process: first schedule the applicable fire inspection through eConnect, then coordinate with the appropriate local fire district when required.
View Lee County’s complete inspection codes and instructions.
Flood-Zone Properties Need Extra Attention in Lee County
Floodplain rules are especially important in Lee County. Construction in a Special Flood Hazard Area may require floodplain review, elevation documentation and substantial-improvement or substantial-damage analysis.
Lee County states that all development in its regulated floodplain needs a local permit. This includes FEMA A, AE, AH and applicable coastal VE flood areas within unincorporated Lee County.
Before remodeling a flood-zone property
- Check the parcel in LeeGIS.
- Identify the current flood zone and base flood elevation information.
- Ask whether substantial-improvement/substantial-damage rules apply.
- Determine whether an Elevation Certificate or other flood documentation will be required.
- Do not begin work until the permit and floodplain requirements are clear.
Lee County does not prepare Elevation Certificates for applicants. They are generally prepared by appropriately licensed surveyors and submitted as part of applicable permit requirements.
Owner-Builder or Licensed Contractor?
Lee County permits commonly involve either a properly licensed and registered contractor or a property owner who qualifies to act as an owner-builder under Florida law.
Using an owner-builder permit does not simply mean hiring someone else to act as an unlicensed general contractor. The owner takes responsibility for the permit, supervision and statutory owner-builder obligations.
If using a contractor, verify licensing and registration before attaching that contractor to the permit. Contractor Licensing can be reached at 239-533-8119.
Before You Start Work: Final Practical Checklist
- Confirm the correct jurisdiction.
- Confirm whether a permit or 2026 exemption request applies.
- Check the property’s flood status.
- Select the correct permit record type.
- Upload the required site/aerial plan and project documents.
- Resolve zoning, development, flood or outside-agency conditions.
- Record the Notice of Commencement when required.
- Pay assessed permit fees.
- Wait until the permit is actually issued.
- Keep approved permit documents available at the project site.
- Schedule inspections at the correct construction stages.
- Do not cover work until required inspections have passed.
- Confirm all finals are passed before treating the project as complete.
- Obtain the applicable Certificate of Occupancy or Certificate of Compliance when required.
A submitted application, paid fee or approved individual review is not the same thing as an issued permit. Check the live eConnect record before beginning regulated construction.
Lee County Building Department FAQs
1. What is the Lee County, Florida Building Department?
Building permitting for unincorporated Lee County is handled through Lee County Community Development — Building & Permitting Services. It manages permit applications, plan review, inspections and related construction services.
2. Where is the Lee County building permit office?
The Community Development office is at 1500 Monroe Street, Fort Myers, FL 33901. Permitting lobby hours are generally Monday through Friday from 9 a.m. to 4 p.m., excluding County holidays.
3. How do I search for a Lee County building permit?
Use the official eConnect Citizen Access portal. You can search permitting records using a permit/record number, address, parcel number and other available criteria.
4. How do I schedule a building inspection in Lee County?
Open eConnect, locate the issued permit and use the inspection scheduling option. Lee County also publishes inspection codes for structural, roofing, electrical, mechanical, plumbing and other inspections.
5. Does Lee County issue permits inside Cape Coral and Bonita Springs?
Normally, incorporated municipalities such as Cape Coral and Bonita Springs use their own local permitting authorities. Confirm the property’s jurisdiction before applying to Lee County.
6. What Florida Building Code is Lee County using in 2026?
As of November 2026, Lee County identifies the Florida Building Code, 8th Edition (2023) for current permitting. The 9th Edition (2026) is scheduled to take effect December 31, 2026.
7. Is work under $7,500 permit-free in Lee County?
Not automatically. Florida’s July 2026 law provides an exemption for qualifying work valued under $7,500 on single-family property, but it excludes flood-hazard properties and electrical, plumbing, structural, mechanical and gas work. A written exemption request with supporting documentation is also required.
8. How much does a Lee County building permit cost?
The cost depends on the permit type, reviews and required inspections. Lee County’s revised fee schedule became effective April 15, 2026 and includes a $50 application fee and $35 technology fee for applicable applications, plus project-specific review and inspection charges.
9. Do I need an account to search Lee County permits?
Basic permit and record searches are available publicly in eConnect without registration. An account is required for actions such as submitting applications and managing certain documents.
10. Who should I call about a Lee County permit or inspection?
For permitting, call 239-533-8329. For plan review, call 239-533-8597. For building inspections, call 239-533-5801. For floodplain questions, call 239-533-8948.
Official Lee County Links for the Final Step
Information reviewed for November 2026. Permit requirements can vary by property, project scope, flood status, zoning and jurisdiction. Use the official portal for the final project-specific determination, application, payment or inspection request.